Rajya Vidyut Utpadan Nigam Ltd.
Inception
Rajasthan Government represented the Rajasthan Rajya Vidyut Utpadan Nigam Ltd. under the Companies Act, 1956 on July 19, 2000. Rajya Vidyut Utpadan Nigam is playing major role in giving uppermost priority to the power production for diverse and swift advancement of the state.
Objective
Rajasthan Rajya Vidyut Utpadan Nigam Ltd. has been trusted with the job of expansion of power projects under state segment, in Rajasthan along with maneuver & repairs of the state owned power stations. The power generation units of Rajya Vidyut Utpadan Nigam Ltd. have attained an idiosyncratic status in the nation for their resourceful and profitable power production.
The total number of villages and towns that were electrified at that time did not surpass 42 and the mounted generation capacity was only 13.27 Mega Watts. Nevertheless, with the configuration of Rajasthan State Electricity Board on July 1, 1957, power sector in the state of Rajasthan received precedence and power projects embarked on to burgeon all over Rajasthan.
Ongoing Projects
Ongoing Projects of Rajya Vidyut Utpadan Nigam Limited are:
S.No | Name of the Unit | Capacity | Expected date of Commissioning |
1 | KALISINDH TPS UNIT I | 600 MW | August 2013 |
2 | KALISINDH TPS UNIT II | 600 MW | November 2013 |
3 | CHHABRA TPS PHASE II (UNIT-3) | 250 MW | August 2013
|
4 | CHHABRA TPS PHASE II (UNIT-4) | 250 MW | December 2013
|
5 | RAMGARH EXTN. PROJECT Stage III STG 50 MW | 50 MW | October 2014
|
| Total | 1750 MW |
|
1 | Ramgarh Gas Thermal Power Project Stage IV GT | 110 MW | October 2014 |
2 | Ramgarh Gas Thermal Power Project Stage IV STG | 50 MW | March 2015 |
3 | Suratgarh Supercritical TPP Unit#7 | 660 MW | September-2016 |
4 | Suratgarh Supercritical TPP Unit#8 | 660 MW | December-2016
|
5 | Chhabra Supercritical TPP Unit#5 | 660 MW | September-2016
|
6 | Chhabra Supercritical TPP Unit#6 | 660 MW | December-2016
|
Comments